by Mike Espeset, President   As a project ramps up, we all join the team at different times and in different ways, with different expectations of what success and joy look like for the project and for one another. Therefor, once we have critical mass of key...
Variance Reasons

Variance Reasons

by Pat Geary, COO   In reviewing Daily Planned Activity Post-It notes at the end of each shift, we mark the notes with a check mark if the activities were completed on that day, and an X if they were not. If the activity receives an X, teams also provide one of...
Post-It Note Requirements

Post-It Note Requirements

by Karlen Anderson, CP 2.0 Program Leader   In order to effectively communicate your team’s planned work activity on site, it’s important your Post-It notes show the right information. This ensures that other teams are aware of your planned work, which will allow...